!HMA-T Progress October 2008 con terra
- None
None
The following documents have been delivered:
- Draft Document on Base and Inspire Conformance Classes of the “OGC Cataloguing of ISO Metadata (CIM) using the ebRIM profile of CS-W� (including some constraints and clarifications on the CSW AP ebRIM EP CIM specification) - uploaded to Wiki
- Draft Abstract Test Suite (ATS) for OGC WRS 1.0 EP CIM - Base- & Inspire Conformance Class - V0.4 13/10/2008 - uploaded to Wiki
- Project report September 2008
Activities performed
- Project Report September
- ebRIM EO Telecon 27.10
- ebRIM CIM Telecon 28.10
Outcomes and results
- Project Report October
Problems and concerns
- none
Plans for next period
- Project Report November
- ebRIM EO Telecon(s)
- ebRIM CIM Telecon(s)
Activities performed
- Identified bugs in base ebRIM/CIM spec
- Familarization with OGC ETS CITE scripts
- Documentation work of Conformance Doc and ATS
- Input for CSW AP ebRIM EP CIM adatations
Outcomes and results
- Draft Document on Base and Inspire Conformance Classes of the “OGC Cataloguing of ISO Metadata (CIM) using the ebRIM profile of CS-W� (including some constraints and clarifications on the CSW AP ebRIM EP CIM specification) - uploaded to Wiki
- Draft Abstract Test Suite (ATS) for OGC WRS 1.0 EP CIM - Base- & Inspire Conformance Class - V0.4 13/10/2008 - uploaded to Wiki
- Input for CSW AP ebRIM EP CIM adatations
Problems and concerns
- none
Plans for next period
- ETS test scripts for base conformance level and maybe for Inspire conformance level
- Input for CSW AP ebRIM EP CIM adatations
- to be started later this year.