HMA-T Progress Terradue 0812

HMA-T Progress December 2008 Terradue

Project Manager Assessment


The status of the project is nominal

Key Problem List


  • None

Risk Table


ID Risk Title                          Severity Likelihood Risk Index Risk Domain Action and status



Deliverables List


  • None.

WP1000: Project Management


Activities performed
 * Progress report

Outcomes and results
  • None.

Problems and concerns
  • None.

Plans for next period
 * Progress report

WP4000


Activities performed

  • Updates to Architecture document
  • Conclusion of System Requirements Document (SRD)
  • Presentation HMA-T Terradue+RAL activities at OGC Valencia

Outcomes and results

Problems and concerns
  • None

Plans for next period
  • Conclusion of Architecture Document
  • Initiate the Acceptance Test Plan
  • Start of HMA-T/G-POD Gateway C# API