HMA-T Progress Terradue 0808

!HMA-T Progress August 2008 Terradue

Project Manager Assessment


The status of the project is nominal considering two weeks holidays

Key Problem List


  • None

Risk Table


ID Risk Title                          Severity Likelihood Risk Index Risk Domain Action and status



Deliverables List


  • None

WP1000: Project Management


Activities performed
  • Contract status check
  • Contract with RAl preparation
  • Preparation of contibution to HMA-T wiki


Outcomes and results

  • Draft Contract for RAL

Problems and concerns
  • None.

Plans for next period
  • Sign Contract with Spacebel
  • Sign Sub-Contract RAL

WP4000


Activities performed

  • Updates in System Requirements Document (SRD)
  • Technologies assessment for the implementation of the project

Outcomes and results

Problems and concerns
  • None

Plans for next period
  • TOC for Architecture document following RM-ODP approach

 