Loading...
 
ESA > Join & Share > HMA-T > HMA-T Progress Spot Image 0903
Print

HMA-T Progress Spot Image 0903

!HMA-T Progress March 2009 Spot Image



Programming


Project Manager Assessment

The status of the project is nominal.

Key Problem List

  • none

Activities performed
  • SPS specification update with examples of requests and responses (Action n° 76)

WP1221: SPS EO Library

  • Activity closed

WP1222: SPS EO server implementation

  • Activity closed

Plans for next period

  • Upload updated version of SPS EO specification on the twiki


Catalogue



Key Problem List

  • none


Activities performed

  • Up to date version of the proxy deployed on Spot Image server

* Two versions deployed : one connected to the DALI catalog (restricted access), one connected to the test version of DALI

Plans for next period

  • Lessons learnt document


Contributors to this page: .

Page last modified on Wednesday 27 of May 2009 14:30:45 CEST by .