HMA-T Progress August 2009 Spacebel

Project Manager Assessment

Progress is nominal. The AR-2 was held July15-16 in ESRIN. 

Key Problem List

*None

Risk Table

ID Risk Title                          Severity Likelihood Risk Index Risk Domain Action and status
1      CITE implementations late 3           2              6              schedule      Monitor technical progress monthly
2      HMA ICD change              2           3              9              cost             Forsee consolidation phase at end.


Deliverables List

The following documents have been delivered:

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 4, 19/08/09.


WP2110: Project Management

Activities performed

  • Update of several Wiki pages to close outstanding actions.
  • Update of open action list and Wiki pages.
  • Contacts and technical discussions with subcontractors (email/phone)
  • Preparation of subcontracts/purchase order for IITB and GIM activities in CCN3.
  • Update of SPMP to take into account CCN3 activities.
  • Normal work

Outcomes and results

  • Updated action list in MS-Excel format.
  • HMAT-SPMP-0002-SPB Issue 1, revision 4.

Problems and concerns

  • Deployed tests at ESRIN do not work correctly.  Several issues foudn by Intecs.
  • OGC 06-131 and OGC 07-038 documents changed at very late stage affecting implementations and CITE tests.
  • Acceptance of IGN, CNR-IMAA and Infoterra activities delayed from july to september.

Plans for next period

  • Participation to OGC TC in September 2009 in Darmstadt.
  • Participation to HMA-FO Meeting during TC in Darmstadt.
  • Participation to HMA-FO Technical Meeting (by teleconference 18 September 2009, PM).


WP2710: Standardisation and Technology Watch

Activities performed

Note that above clients do not yet use the CIM EP 0.1.11 (with changed slots) which was released in early september 2009, but the previous version.

Outcomes and results

  • Normal work.

Problems and concerns

  • None.

Plans for next period

  • Normal work, closure of open actions.
  • Update of OGC 07-118 document once inputs from Intecs become available (See open actions).

Plans for next period

  • Participation to OGC TC in Darmstadt.

 


WP3200: Support to HMA-FO Technical Management

Activities performed

  • Preparation of email lists for each task
  • Initialisation of Wiki structure.

Outcomes and results

  • Normal work.

Problems and concerns

  • None.

Plans for next period

  • Normal work.
  • Preparation of technical teleconference 18 september.

 


WP3300: HMA Standards Cookbook

Activities performed

  • Workpackage not yet started.

Outcomes and results

  • Normal work.

Problems and concerns

  • None.

Plans for next period

  • None.

 


WP3400: Identity and Access Management

Activities performed

  • Finalisation of open-source implementation of authentication service.
  • testing of open-source implementation authentication encryption/decryption/signatures in cooperation with Intecs;
  • Preparation of SRD, ADD and ATP documents for above software.

Outcomes and results

  • Normal work.

Problems and concerns

  • None.

Plans for next period

  • Finalisation of open-source authentication service implementation and associated documents.
  • Participation to UM teleconference 14 september at 14h00 with Conterra, ESA and others.