HMA-T Progress Spacebel 0906

HMA-T Progress June 2009 Spacebel

Project Manager Assessment

Progress is nominal. The AR-2 has been fixed July15-16 in ESRIN.

Key Problem List

*None

Risk Table

ID Risk Title                          Severity Likelihood Risk Index Risk Domain Action and status
1      CITE implementations late 3           2              6              schedule      Monitor technical progress monthly
2      HMA ICD change              2           3              9              cost             Forsee consolidation phase at end.


Deliverables List

The following documents have been delivered:

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.


WP2110: Project Management

Activities performed

  • Update of several Wiki pages to close outstanding actions.
  • Update of open action list and Wiki pages.
  • Contacts and technical discussions with subcontractors (email/phone)
  • Technical Meeting 11/06/2009 in ESRIN with CNR-IMAA, Intecs and ESA.
  • Participation and presentation at GSCB meeting in ESRIN June 18-19 2009.
  • KO Meeting HMA-T CCN3 activities June 11 2009.
  • Normal work

Outcomes and results

  • Updated action list in MS-Excel format.
  • Minutes of meeting 11 June 2009.

Problems and concerns

  • Deployment of consolidated CITE CTL tests on TEAM Web pages at ESRIN still underway.
  • Slow finalisation of OGC 06-131 and OGC 07-038 documents.
  • ESA endpoint information is not yet available on Wiki.  ESA catalogue has no accessible GetCapabilities operation.
  • Late availability of consolidated CITE scripts for EO EP and CIM EP.

Plans for next period

  • Participation and organisation of AR-2 meeting 15-16 July 2009.
  • Participation to HMA-FO KO Meeting 24 June in ESRIN.


WP2710: Standardisation and Technology Watch

Activities performed

Outcomes and results

  • Normal work.

Problems and concerns

  • None.

Plans for next period

  • Normal work, closure of open actions.
  • Update of OGC 07-118 document once inputs from Intecs become available (See open actions).

Plans for next period

  • Finalisation of CNR-IMAA GI-CAT Client implementation and test.

 


WP3200: Support to HMA-FO Technical Management

Activities performed

  • Preparation of HMA-FO KO 24 June 2009.
  • Review of various Proposals
  • Preparation of presentation for KO.

Outcomes and results

  • Normal work.

Problems and concerns

  • None.

Plans for next period

  • Initialisation of Wiki structure and creation of email aliases.

 


WP3300: HMA Standards Cookbook

Activities performed

  • Workpackage not yet started.

Outcomes and results

  • Normal work.

Problems and concerns

  • None.

Plans for next period

  • None.

 


WP3400: Identity and Access Management

Activities performed

  • Analysis of EO-DAIL auithentication service implementation and replacement of OID with OpenLDAP

Outcomes and results

  • Normal work.

Problems and concerns

  • None.

Plans for next period

  • Finalisation of open-source authentication service implementation and inclusion in HMA Skeleton.


Contributors to this page: .

Page last modified on Friday 10 of July 2009 15:36:36 CEST by .