HMA-T Progress Spacebel 0906
HMA-T Progress June 2009 Spacebel
Progress is nominal. The AR-2 has been fixed July15-16 in ESRIN.
*None
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
1 | CITE implementations late | 3 | 2 | 6 | schedule | Monitor technical progress monthly |
2 | HMA ICD change | 2 | 3 | 9 | cost | Forsee consolidation phase at end. |
The following documents have been delivered:
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.
Activities performed
- Update of several Wiki pages to close outstanding actions.
- Update of open action list and Wiki pages.
- Contacts and technical discussions with subcontractors (email/phone)
- Technical Meeting 11/06/2009 in ESRIN with CNR-IMAA, Intecs and ESA.
- Participation and presentation at GSCB meeting in ESRIN June 18-19 2009.
- KO Meeting HMA-T CCN3 activities June 11 2009.
- Normal work
Outcomes and results
- Updated action list in MS-Excel format.
- Minutes of meeting 11 June 2009.
Problems and concerns
- Deployment of consolidated CITE CTL tests on TEAM Web pages at ESRIN still underway.
- Slow finalisation of OGC 06-131 and OGC 07-038 documents.
- ESA endpoint information is not yet available on Wiki. ESA catalogue has no accessible GetCapabilities operation.
- Late availability of consolidated CITE scripts for EO EP and CIM EP.
Plans for next period
- Participation and organisation of AR-2 meeting 15-16 July 2009.
- Participation to HMA-FO KO Meeting 24 June in ESRIN.
Activities performed
- Client development completed in SSE for CNR-IMAA test endpoint (few collections). Available at http://hma.spacebel.be/portal/order/PrepareOperation.do?serviceId=B2818580&operation=Search.
- Client development in SSE started for CNR-IMAA endpoint providing access to NASA collections (few collections). Several issues still pending. Waiting for CNR-IMAA to upgrade their server software for this catalogue. Available at http://hma.spacebel.be/portal/order/PrepareOperation.do?serviceId=B4818080&operation=Search.
Outcomes and results
- Normal work.
Problems and concerns
- None.
Plans for next period
- Normal work, closure of open actions.
- Update of OGC 07-118 document once inputs from Intecs become available (See open actions).
Plans for next period
- Finalisation of CNR-IMAA GI-CAT Client implementation and test.
Activities performed
- Preparation of HMA-FO KO 24 June 2009.
- Review of various Proposals
- Preparation of presentation for KO.
Outcomes and results
- Normal work.
Problems and concerns
- None.
Plans for next period
- Initialisation of Wiki structure and creation of email aliases.
Activities performed
- Workpackage not yet started.
Outcomes and results
- Normal work.
Problems and concerns
- None.
Plans for next period
- None.
Activities performed
- Analysis of EO-DAIL auithentication service implementation and replacement of OID with OpenLDAP
Outcomes and results
- Normal work.
Problems and concerns
- None.
Plans for next period
- Finalisation of open-source authentication service implementation and inclusion in HMA Skeleton.