HMA-T Progress Spacebel 0904

HMA-T Progress April 2009 Spacebel

Project Manager Assessment

Due to the consolidation of the CITE activities taking longer than expected, the AR-2 is expected to be moved to middle of July (Week of 13 July).

Key Problem List

*None

Risk Table

ID Risk Title                          Severity Likelihood Risk Index Risk Domain Action and status
1      CITE implementations late 3           2              6              schedule      Monitor technical progress monthly
2      HMA ICD change              2           3              9              cost             Forsee consolidation phase at end.
4      Unstable TEAM engine       3           2              6              quality         Early tests in ERGO


Deliverables List

The following documents have been delivered:

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.


WP2110: Project Management

Activities performed

  • Update of several Wiki pages to close outstanding actions.
  • Update of open action list and Wiki pages.
  • Organisation and participation to technical meeting with IGN, ERDAS and ESA April 30 2009 in Hoeilaart.
  • Finalisation of HMA-T CCN3 Proposal.
  • Normal work

Outcomes and results

  • Updated action list in MS-Excel format.
  • Minutes of technical meeting 30 April 2009.

Problems and concerns

  • TEAM engine to be deployed at ESRIN soon.
  • Deployment of consolidated CITE CTL tests on TEAM Web pages at ESRIN.
  • Installation of Deimos SPS at ESRIN seems to make very slow progress.
  • Not all endpoint information is available on the Wiki yet.

Plans for next period

  • Participation and presentation at GSCB meeting in ESRIN June 18-19 2009.
  • Organisation of AR-2 meeting(s).

 

WP2710: Standardisation and Technology Watch

Activities performed

  • Participation at OGC TC in Athens, including CITE SC where CTL (with SOAP tag) was proposed as Best Practice.
  • Investigation of various OGC 06-131 implementation issues found in Spotimage and ESA endpoints.  Discussion of these with Spotimage, ERDAS and ESRIN.
  • Completion of OGC 06-131 version 0.2.2 client connected to Spot Image Dali catalogue, available on http://hma.spacebel.be.  Made available to Spotimage for demo at Stresa in framework of GEOSS AIP-2.

Outcomes and results

  • Normal work.

Problems and concerns

  • None.

Plans for next period

  • Normal work, closure of open actions.
  • Update of OGC 07-118 document once inputs from Intecs become available (See open actions).


 