HMA-T Progress Spacebel 0901
!HMA-T Progress January 2009 Spacebel
The status of the project is nominal with the exception of Infoterra-Uk which has extended their planning from short (AR-1) to long (up to AR-2).
*None
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
1 | CITE implementations late | 3 | 2 | 6 | schedule | Monitor technical progress monthly |
2 | HMA ICD change | 2 | 3 | 9 | cost | Forsee consolidation phase at end. |
4 | Unstable TEAM engine | 3 | 2 | 6 | quality | Early tests in ERGO |
The following documents have been delivered:
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.
Activities performed
- Update of several Wiki pages to close outstanding actions.
- Synchronisation with FEDEO Support activities which have been started.
- Synchronisation with Framecontract skeleton development tasks
- Tracking of agreed actions.
- Communication with Spot image related to access to 06-131 end-point and firewall issues.
- Investigation of ISO19139 issues and preparation of metadata examples with support from ERDAS and Spotimage.
- Preparation of AR-1 meeting, planned for February 18-19 2009.
Outcomes and results
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.
Problems and concerns
- Update of OGC 07-118 (User Management) document by EO-DAIL project has been delayed. New expected date is middle of february.
- Missing planning from IGN addressing current delays.
Plans for next period
- Organisation and preparation of AR-1 and CDR meeting February 18-19 2009 and review of submitted deliverables.
- Participation to discovery/ontology workshop in ESRIN 4 march.
Activities performed
- Investigation of ISO19139 issues with schemas and approach for metadata definition, also in relation with the INSPIRE MD Guidance document.
- Preparation of OGC 06-131 version 0.2.2 client to be connected to Spot Image Dali catalogue has started.
Outcomes and results
- None
Problems and concerns
- Resolving firewall issues to access Spot Image OGC 06-131 service delayed start implementation. Issues should be resolved by know.
Plans for next period
- Completion of OGC 06-131 version 0.2.2 client to be connected to Spot Image Dali catalogue.