!HMA-T Progress January 2009 Spacebel

Project Manager Assessment

The status of the project is nominal with the exception of Infoterra-Uk which has extended their planning from short (AR-1) to long (up to AR-2).

Key Problem List

*None

Risk Table

ID Risk Title                          Severity Likelihood Risk Index Risk Domain Action and status
1      CITE implementations late 3           2              6              schedule      Monitor technical progress monthly
2      HMA ICD change              2           3              9              cost             Forsee consolidation phase at end.
4      Unstable TEAM engine       3           2              6              quality         Early tests in ERGO


Deliverables List

The following documents have been delivered:

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.


WP2110: Project Management

Activities performed

  • Update of several Wiki pages to close outstanding actions.
  • Synchronisation with FEDEO Support activities which have been started.
  • Synchronisation with Framecontract skeleton development tasks
  • Tracking of agreed actions.
  • Communication with Spot image related to access to 06-131 end-point and firewall issues.
  • Investigation of ISO19139 issues and preparation of metadata examples with support from ERDAS and Spotimage.
  • Preparation of AR-1 meeting, planned for February 18-19 2009.

Outcomes and results

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.

Problems and concerns

  • Update of OGC 07-118 (User Management) document by EO-DAIL project has been delayed.  New expected date is middle of february.
  • Missing planning from IGN addressing current delays.

Plans for next period

  • Organisation and preparation of AR-1 and CDR meeting February 18-19 2009 and review of submitted deliverables. 
  • Participation to discovery/ontology workshop in ESRIN 4 march.

 

WP2710: Standardisation and Technology Watch

Activities performed

  • Investigation of ISO19139 issues with schemas and approach for metadata definition, also in relation with the INSPIRE MD Guidance document.
  • Preparation of OGC 06-131 version 0.2.2 client to be connected to Spot Image Dali catalogue has started.

Outcomes and results

  • None

Problems and concerns

  • Resolving firewall issues to access Spot Image OGC 06-131 service delayed start implementation.  Issues should be resolved by know.

Plans for next period

  • Completion of OGC 06-131 version 0.2.2 client to be connected to Spot Image Dali catalogue.


 