Project Manager Assessment

The status of the project is nominal, with the exception of the CITE tasks from IGN which have incurred a delay of about two months.  IGN will propose an updated planning to limit the delay and the impact on the other partners.

Key Problem List

*None

Risk Table

ID Risk Title                          Severity Likelihood Risk Index Risk Domain Action and status
1      CITE implementations late 3           2              6              schedule      Monitor technical progress monthly
2      HMA ICD change              2           3              9              cost             Forsee consolidation phase at end.
4      Unstable TEAM engine       3           2              6              quality         Early tests in ERGO


Deliverables List

The following documents have been delivered:

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.


WP2110: Project Management

Activities performed

  • Update of several Wiki pages to close outstanding actions.
  • Participation to OGC TC in Valencia from 1 to 4 december.
  • Synchronisation with FEDEO Support activities which have been started.
  • Tracking of agreed actions.

Outcomes and results

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.

Problems and concerns

  • Update of OGC 07-118 (User Management) document by EO-DAIL project has been delayed.
  • Updated 06-131 Version 0.2.2 not yet supported by HMA Skeleton 2.0.  Framecontract to update the simulation files accordingly;
  • Missing planning from IGN addressing current delays.

Plans for next period

  • Organisation and preparation of AR-1 meeting, currently planned for February 18-19 2009.  Dates are to be confirmed. 

 

WP2710: Standardisation and Technology Watch

Activities performed

  • Participation to OGC TC Meeting in Valencia (Security, Architecture, EO/CIM ext. SWG, Europe Forum).
  • HMA-T presentation with support from subcontractors at Europe Forum.
  • Investigation of ISO19139 issues with schemas and approach for metadata definition, also in relation with the INSPIRE MD Guidance document.
  • Preparing inputs for ESA User Management presentation to HMA Architecture Board in Valencia.

Outcomes and results

  • None

Problems and concerns

  • None

Plans for next period

  • Preparation of OGC 06-131 version 0.2.2 client to be connected to Spot Image Dali catalogue.


 