HMA-T Progress Spacebel 0810

HMA-T Progress October 2008 Spacebel

Project Manager Assessment


The status of the project is nominal.

Key Problem List

  • None

Risk Table

ID Risk Title Severity Likelihood Risk Index Risk Domain Action and status
1 CITE implementations late 3 2 6 schedule Monitor technical progress monthly
2 HMA ICD change 2 3 9 cost Forsee consolidation phase at end.
3 Unstable TEAM engine 3 2 6 quality Early tests in ERGO


Deliverables List


The following documents have been delivered:

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.


WP2110: Project Management


Activities performed

  • Tracking of actions and update of on-line actions database.
  • Update of several Wiki pages to close outstanding actions.
  • This month subcontracts with ERDAS and CNR-IMAA have been signed.
  • Discussion with ESA and Spot Image regarding contractual non-compliances in proposed Spot Image subcontract. Agreement with ESA was reached. ESA will send a CCN which has not yet been received.


Outcomes and results

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.


Problems and concerns

  • Update of OGC 07-118 (User Management) document by EO-DAIL project has been delayed.
  • Updated 06-131 Version 0.2.0 not yet supported by HMA Skeleton 2.0. Framecontract to update the simulation files accordingly.
  • Terradue has not provided a single progress report since the KO.


Plans for next period

  • Check status of subcontractor invoices in EFIS following inquiries from ERDAS and Infoterra-UK.
  • Preparation of HMA-T technical meeting and teleconference in Spacebel (Hoeilaart).
  • Review of draft deliverables already available on the Wiki in-time for the foreseen teleconference/meeting.
  • Resolution of contractual issue with Spot Image.
  • Signing remaining subcontracts with Spot Image.

WP2710: Standardisation and Technology Watch


Activities performed

  • Spacebel has registered the HMA skeleton catalogue (opt/sar/eop) on the SSE Test Portal. A link to the demo catalogues was added on the HMA Skeleton Wiki Page.


Outcomes and results

  • None


Problems and concerns

  • None


Plans for next period

  • Preparation of presentations at OGC TC catalogue working group.
  • Participation to OGC TC Meeting in Valencia.
  • Participation to HMA WG in Valencia.