HMA-T Progress Spacebel 0809

HMA-T Progress September 2008 Spacebel

Project Manager Assessment


The status of the project is nominal.

Key Problem List

  • None

Risk Table

ID Risk Title Severity Likelihood Risk Index Risk Domain Action and status
1 CITE implementations late 3 2 6 schedule Monitor technical progress monthly
2 HMA ICD change 2 3 9 cost Forsee consolidation phase at end.
3 Unstable TEAM engine 3 2 6 quality Early tests in ERGO


Deliverables List


The following documents have been delivered:

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.


WP2110: Project Management


Activities performed

  • Update of project management plan.
  • Setup of on-line action tracking system
  • Participation to technical meeting related to SPS at Spotimage (9 september).
  • subcontracts with IGN-F, Infoterra-UK, GIM, Con terra, Intecs, Deimos and Terradue have been signed.
  • CCN for Phase 2 with ESA has been signed by ESA and Spacebel.


Outcomes and results

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.


Problems and concerns

  • Update of OGC 07-118 (User Management) document by EO-DAIL project has been delayed.
  • Updated 06-131 Version 0.2.0 not yet supported by HMA Skeleton 2.0. Framecontract to update the simulation files accordingly.
  • Spot Image requests changes to their subcontract which are not inline with the ESA draft contract. ESA has been informally requested to allow for a Waiver.
  • No signed subcontract from CNR-IMAA has been received.
  • CNR-IMAA email addresses are unreliable and emails bounce back in a random fashion. Alternative email addresses have been provided by CNR-IMAA for use in the email alias.


Plans for next period

  • Preparation of HMA-T technical meeting 22 october in Spacebel (Hoeilaart).
  • Resolution of contractual issue with Spot Image.
  • Signing remaining subcontracts with ERDAS, CNR-IMAA, Spot Image.

WP2710: Standardisation and Technology Watch


Activities performed

  • Spacebel has registered the HMA skeleton catalogue (opt/sar/eop) on the SSE Test Portal. A link to this demo will be added on the HMA Skeleton Wiki Page.


Outcomes and results

  • None


Problems and concerns

  • None


Plans for next period

  • Preparation of presentations at OGC TC catalogue working group related to catalogue and CITE.
  • Participation to OGC TC Meeting in Valencia.
  • Participation to HMA WG in Valencia.