HMA-T Progress Spacebel 0808

HMA-T Progress August 2008 Spacebel

Project Manager Assessment


The status of the project is nominal.

Key Problem List

  • None

Risk Table

ID Risk Title Severity Likelihood Risk Index Risk Domain Action and status
1 CITE implementations late 3 2 6 schedule Monitor technical progress monthly
2 HMA ICD change 2 3 9 cost Forsee consolidation phase at end.
3 Unstable TEAM engine 3 2 6 quality Early tests in ERGO


Deliverables List


The following documents have been delivered:

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.


WP2110: Project Management


Activities performed

  • Update of project management plan.
  • Setup of on-line action tracking system
  • Organisation of HMA-T Wiki structure
  • Preparation of subcontracts. All subcontractors have received their subcontract early august for signature.
  • CCN from ESA was received and will be sent to ESA in coming days.
  • Informal discussion with Spotimage related to the issues with the new SPS specification.


Outcomes and results

  • HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.


Problems and concerns

  • Impact of forthcoming 07-018 EO Profile for SPS.
  • Updated 06-131 Version 0.2.0 not yet supported by HMA Skeleton 2.0. Framecontract to update the simulation files accordingly.
  • Some subcontractors want to renegotiate content of their subcontract which is based on ESA draft contract.


Plans for next period

  • Preparation of technical meeting 9 september in Toulouse.
  • Signing subcontracts.

WP2710: Standardisation and Technology Watch


Activities performed
This activity is scheduled to start 01/09/2008.

Outcomes and results

  • None


Problems and concerns

  • None


Plans for next period

  • Participation to technical meeting about new version of SPS at Spot Image in Toulouse (September 9 2008). Topics to be addressed: synchronous operations, use of ws-notification, impact on ordering ICD etc.
  • Preparation of presentations at OGC TC catalogue working group related to catalogue and CITE.
  • Participation to OGC TC Meeting in Valencia.
  • Participation to HMA WG in Valencia.