HMA-T Progress Spacebel 0807
HMA-T Progress July 2008 Spacebel
The status of the project is nominal.
- None
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
1 | CITE implementations late | 3 | 2 | 6 | schedule | Monitor technical progress monthly |
2 | HMA ICD change | 2 | 3 | 9 | cost | Forsee consolidation phase at end. |
3 | Unstable TEAM engine | 3 | 2 | 6 | quality | Early tests in ERGO |
The following documents have been delivered:
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 2, 25/06/08.
Activities performed
- Organisation of Negotiation and Kick-off meeting in ESRIN, 2-3 July 2008.
- Preparation of project Management Plan version 1.2
- Creation of email alias for HMA-T.
Outcomes and results
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 2, 25/06/08.
Problems and concerns
- Impact of forthcoming 07-018 EO Profile for SPS.
- Updated 06-131 Version 0.2.0 not yet supported by HMA Skeleton 2.0. Framecontract to update the simulation files accordingly.
Plans for next period
- Preparation of progress reporting structure on HMA-T Wiki.
- Update of SPMP incorporating updated list of subcontractor deliverables.
- Preparation of subcontracts
- Preparation of accounts on action tracking system PVCS for all subcontractors.
- preparation of list of teleconferences and powownow account for HMA-T.
Activities performed
This activity is scheduled to start 01/09/2008.
Outcomes and results
- None
Problems and concerns
- None
Plans for next period
- Participation to technical meeting about new version of SPS at Spot Image in Toulouse (September 9 2008). Topics to be addressed: synchronous operations, use of ws-notification, impact on ordering ICD etc.
- Preparation of presentations at OGC TC catalogue working group related to catalogue and CITE.
- Participation to OGC TC Meeting in Valencia.
- Participation to HMA WG in Valencia.