HMA-T Progress Infoterra 0910

HMA-T Progress October 2009 Infoterra Ltd.

Project Manager Assessment

The status of the project is nominal.

Key Problem List

  • None

Risk Table

ID Risk Title                          Severity Likelihood Risk Index Risk Domain Action and status


Deliverables List

No documents were delivered this month.

WP1100: Project Management

Activities performed
  • Resource Planning
  • Progress Planning

Outcomes and results

  • Internal project reporting

Problems and concerns
  • None

Plans for next period
  • Review progress on Actions

 

WP4100: Aceptance Test Plan

 Activities performed

  • Finalisation of plan.


Outcomes and results

  • Submission for internal review.


Problems and concerns

  • None

Plans for next period
  • Update, based on internal review comments, and delivery.

 

WP4300: Installation guide

 Activities performed

  • Installation and Operations Manual (IOM) finalisation.


Outcomes and results

  • Submission for internal review.


Problems and concerns

  • None

Plans for next period
  • Update, based on internal review comments, and delivery.

 

WP4500: Acceptance Test Report

 Activities performed

  • Aceptance Test Report (ATR) finalisation.

 

Outcomes and results

  • Submission for internal review.


Problems and concerns

  • None

Plans for next period
  • Update, based on internal review comments, and delivery