HMA-T Progress Infoterra 0909

HMA-T Progress September 2009 Infoterra Ltd.

Project Manager Assessment

The status of the project is nominal.

Key Problem List

  • None

Risk Table

ID Risk Title                          Severity Likelihood Risk Index Risk Domain Action and status


Deliverables List


WP1100: Project Management

Activities performed
  • Resource Planning
  • Progress Planning

Outcomes and results

  • Internal project reporting

Problems and concerns
  • None

Plans for next period
  • Review progress on Actions

 

WP4100: Aceptance Test Plan

 Activities performed

  • Started plan update.


Outcomes and results

  • None.


Problems and concerns

  • None

Plans for next period
  • Finalise ATP and submit for internal review.

 

WP4300: Installation guide

 Activities performed

  • Update of Installation and Operations Manual (IOM) with operational instructions on how to insert additional datasets into the WMS server


Outcomes and results

  • Updated IOM.


Problems and concerns

  • None

Plans for next period
  • Internal review of IOM.

 

WP4500: Acceptance Test Report

Activities performed

  • Performed CITE acceptance testing on Reference Implementation installed at Infoterra 
  • Started update of ATR

 

Outcomes and results

  • CITE test comparison of the modified MapServer WMS against an unmodified one.


Problems and concerns

  • None

Plans for next period
  • Finalise ATR for internal review.