HMA-T Progress Infoterra 0813

HMA-T Progress January 2009 Infoterra Ltd.

Project Manager Assessment

The status of the project is nominal.

Key Problem List

  • None

Risk Table

ID Risk Title                          Severity Likelihood Risk Index Risk Domain Action and status


Deliverables List

The following documents have been delivered:
Updated WMS EO Application Profile, OGC-07-063r1, 31/10/2008

WP1100: Project Management

Activities performed
  • Resource Planning
  • Progress Planning

Outcomes and results

  • Map server configuration and data load progressing

Problems and concerns
  • None

Plans for next period
  • Review progress of reference implementation

 


WP2100: OGC WMS EO extension update

Activities performed
  • None

Outcomes and results
  • Awaiting outcome of OGC e-vote on WMS EO extension update (OGC-07-063r1).

Problems and concerns
  • None

Plans for next period
  • Final revision of the WMS EO extension (OGC-07-063r1) document based on RIDs and subsequent discussions with reviewers.
 

WP3100: Reference Implementation Development

Activities performed
  • Use of Deegree to support the implementation of sample dimensions for the interactive viewing of band data via the WMS EO server.

Outcomes and results
  • None.

Problems and concerns
  • None

Plans for next period
  • Complete reference implementation development


Contributors to this page: Thomas Lankester .

Page last modified on Wednesday 18 of February 2009 13:57:48 CET by Thomas Lankester.

Category: HMA-T