HMA-T Progress Infoterra 0807

HMA-T Progress July 2008 Infoterra Ltd.

Project Manager Assessment


The status of the project is nominal.

Key Problem List

  • None

Risk Table

ID Risk Title Severity Likelihood Risk Index Risk Domain Action and status


Deliverables List


The following documents have been delivered:

WP1100: Project Management


Activities performed

  • Project manager appointed
  • Attended Negotiation and Kick-off meeting in ESRIN, 2-3 July 2008.
  • Internal project launch.


Outcomes and results

  • Creation of detailed workpackage breakdown.
  • Defined specific staff resource requirements to end 2008.


Problems and concerns

  • None.


Plans for next period

  • Sign sub-contract with Spacebel
  • Submit invoice via EFIS

WP1300: Technical Management


Activities performed

  • Defined technical specification for server hardware


Outcomes and results

  • Server hardware ordered


Problems and concerns

  • None


Plans for next period

  • Set up Infoterra contribution wiki page.
  • Make July progress report.