HMA-T Progress IGN 0907


HMA-T Progress July 2009 IGN

WP0 - Management

Activities performed

  • Attended AR2 meeting


Plans for next period

  • None

WP1 - Improve the test policies and procedures

Activities performed

  • None


Plans for next period

  • Add guidelines for ETS

WP2 - Develop CITE conformance test scripts for HMA Catalog Protocol OGC 06-131

Activities performed

  • Worked on consolidated ETS development, including integration of binding abstraction
  • Interactions with Erdas to correct and enhance the scripts


Plans for next period

  • Finalize consolidated ETS

WP3 - Develop CITE conformance test scripts for HMA Catalog Protocol OGC 07-038

Activities performed

  • Worked on consolidated ETS development, including integration of binding abstraction
  • Interactions with Erdas to correct and enhance the scripts


Plans for next period

  • Finalize consolidated ETS