HMA-T Progress IGN 0901

HMA-T Progress January 2009 IGN

WP0 - Management


Activities performed

  • None


Plans for next period

  • Attend AR1

WP1 - Improve the test policies and procedures


Activities performed

  • Finalized Draft 2 of HMA Test P&P taking more fully into account the OGC Policy SWG document


Plans for next period

  • Take into account comments on the document

WP2 - Develop CITE conformance test scripts for HMA Catalog Protocol OGC 06-131


Activities performed

  • None


Outcomes and results

  • None


Problems and concerns

  • Temporary lack of resource leads to delays in WP2 and 3. Expected overall delay: 2 to 3 months


Plans for next period

  • Propose way forward for harmonized CITE tests for EO EP in OGC (to be presented during AR1)


WP3 - Develop CITE conformance test scripts for HMA Catalog Protocol OGC 07-038


Activities performed

  • None


Outcomes and results

  • None


Problems and concerns

  • Temporary lack of resource leads to delays in WP2 and 3. Expected overall delay: 2 to 3 months


Plans for next period

  • Propose way forward for harmonized CITE tests for CIM EP in OGC (to be presented during AR1)