HMA-T Progress IGN 0812
HMA-T Progress December 2008 IGN
WP0 - Management
Activities performed
- Presented HMA-T Catalog Protocols Conformance & Testing at OGC TC
Plans for next period
- None
WP1 - Improve the test policies and procedures
Activities performed
- Read the latest version of the Policy SWG document
- First plans on how to edit the HMA Test P&P
Plans for next period
- Finalize Draft 2 of HMA Test P&P
WP2 - Develop CITE conformance test scripts for HMA Catalog Protocol OGC 06-131
Activities performed
- Read ATS developed by CNR and con terra in order to identify a way forward for harmonized ATSs for HMA-T Catalog Protocols
Outcomes and results
- None
Problems and concerns
- Temporary lack of resource leads to delays in WP2 and 3. Expected overall delay: 2 to 3 months
Plans for next period
- Work on a Core ATS
WP3 - Develop CITE conformance test scripts for HMA Catalog Protocol OGC 07-038
Activities performed
- Read ATS developed by CNR in order to identify a way forward for harmonized ATSs for HMA-T Catalog Protocols
Outcomes and results
- None
Problems and concerns
- Temporary lack of resource leads to delays in WP2 and 3. Expected overall delay: 2 to 3 months
Plans for next period
- Work on a Core ATS