HMA-T Progress GIM 0908

Project Manager Assessment

The status of the project is nominal.

Key Problem List

  • None

Deliverables Table

  • HMAT-TN-0002-GIM-12: Technical Note on the application of the GML 3.1.1 Application Schema for EO Products to the VITO EO product collections
  • HMAT-TN-0003-GIM-11: Technical Note on the design of the HMA EO Product Catalogue for VITO CVB
  • HMAT-ATP-0001-GIM-10: Acceptance Test Plan
  • HMAT-ATR-0001-GIM-10: Acceptance Test Report

WP1000 Project Management (GIM)

Activities performed

  • Contacts with subcontractors

Outcome and results

Problems and concerns

  • None.

Plans for next period

  • Normal work
  • Resolution of AR2 actions

WP2000 Application of EO Profile of GML for VITO Products (GIM)

Activities performed


Outcome and results

Problems and concerns

  • None

Plans for next period

  • None

WP3000 Integrate and demonstrate VITO HMA Catalog within HMA-I Prototype (GIM)

Activities performed

  • Finetuning of portal integration

Outcome and results

Problems and concerns

  • None

Plans for next period

  • Rerun acceptance tests once consolidated set of tests will be available
  • Update Catalogue installation with new ERDAS Catalogue software


WP4000 Evaluation of EO Profile of GML and provision of metadata (VITO)

Activities performed

Outcome and results

Problems and concerns

  • None

Plans for next period

  • discuss with GIM potential improvements to portal integration

WP5000 Evaluation of EO Profile of GML and provision of “adapted� EO Proxy framework and support (ERDAS)

Activities performed

  • Update of Catalog software ongoing

Outcome and results

Problems and concerns

  • None

Plans for next period

  • Release of new ERDAS Catalog software to GIM