Project Manager Assessment

The status of the project is nominal.

Key Problem List

  • None

Deliverables Table

  • HMAT-TN-0002-GIM-12: Technical Note on the application of the GML 3.1.1 Application Schema for EO Products to the VITO EO product collections
  • HMAT-TN-0003-GIM-11: Technical Note on the design of the HMA EO Product Catalogue for VITO CVB
  • HMAT-ATP-0001-GIM-10: Acceptance Test Plan
  • HMAT-ATR-0001-GIM-10: Acceptance Test Report

WP1000 Project Management (GIM)

Activities performed

  • Discussions with ERDAS and Spacebel on light extension package approaches.
  • Integration testing of SSE WebMapViewer with IT UK EO Profile of WMS Server, third round of tests.
  • Preparation of and attendance to the HMAT AR2 Meeting on 15-16/07 at ESRIN

Outcome and results

  • AR2 Presentation slides

Problems and concerns

  • None.

Plans for next period

  • Normal work
  • Resolution of AR2 actions

WP2000 Application of EO Profile of GML for VITO Products (GIM)

Activities performed

  • Update of Document for AR2 addressing all RIDs

Outcome and results

  • HMAT-TN-0002-GIM-12

Problems and concerns

  • None

Plans for next period

  • None

WP3000 Integrate and demonstrate VITO HMA Catalog within HMA-I Prototype (GIM)

Activities performed

  • Updating of Design technical note
  • Analysis of compliance test reports and rerunning of compliance tests of IGN, CNR and INTECS.
  • To prove that some issues are due to the use of the extended schema, a separate catalogue instance was installed that only uses the eop schemas.
  • Develop Workflow and HMA portal integration files for 2 demonstration Services
  1. a catalogue instance that uses the GetRecords and GetRecordById operation
  2. a catalogue instance that uses the GetRecords and GetRepositoryItem operation with custom developed workflows to allow visulisation of extended metadata

Outcome and results

Problems and concerns

  • None

Plans for next period

  • Rerun acceptance tests once consolidated set of tests will be available
  • Update Catalogue installation with new ERDAS Catalogue software
  • Finetune portal integration

WP4000 Evaluation of EO Profile of GML and provision of metadata (VITO)

Activities performed

Outcome and results

Problems and concerns

  • None

Plans for next period

  • discuss with GIM potential improvements to portal integration

WP5000 Evaluation of EO Profile of GML and provision of “adapted� EO Proxy framework and support (ERDAS)

Activities performed

  • Discussions with GIM and others on compliance testsing

Outcome and results

Problems and concerns

  • None

Plans for next period

  • Release of new ERDAS Catalog software