HMA-T Progress GIM 0809

Project Manager Assessment

The status of the project is nominal.

Key Problem List
  • None
Deliverables Table

WP1000 Project Management (GIM)

Activities performed

  • Subcontracts created and dispatched to VITO and ERDAS
  • Subcontract GIM-ERDAS signed by both partners

Outcome and results

Problems and concerns

  • None.

Plans for next period

  • Signing of Subcontract GIM-VITO

WP2000 Application of EO Profile of GML for VITO Products (GIM)

Activities performed

  • Continue mapping of existing metadata on EO Profile of GML
  • First review of OGC06-080r4
  • First review of OGC06-131r4: Comments submitted to ERDAS and included in r5
  • Participation to EO Extension Package RWG teleconf on 22/09

Outcome and results

Problems and concerns

  • First internal draft of metadata mapping TN

Plans for next period

  • Participation to EO Extension Package RWG teleconf on 10/10
  • continue mapping of existing metadata on EO Profile of GML
  • Issue Draft TN
WP3000 Integrate and demonstrate VITO HMA Catalog within HMA-I Prototype (GIM)

Activities performed

Not started yet

Outcome and results

Problems and concerns

Plans for next period

WP4000 Evaluation of EO Profile of GML and provision of metadata (VITO)

Activities performed

  • delivery of metadata

Outcome and results

Problems and concerns

Plans for next period

  • Assist GIM in mapping of metadata

WP5000 Evaluation of EO Profile of GML and provision of “adapted� EO Proxy framework and support (ERDAS)

Activities performed

  • discussion on use of TypeNames in OGC06-161

Outcome and results

Problems and concerns

Plans for next period

  • Assist GIM in mapping of metadata