HMA-T Progress DEIMOS 0906

!HMA-T Progress June 2009 DEIMOS

Project Manager Assessment


The status of the project is nominal.

Key Problem List

  • None

Risk Table

  • None

Deliverables List

  • Software Requirements Document has been reviewed
  • Architecture Design Document has been reviewed
  • System Test Specification Document has been reviewed
  • Software installed at ESRIN.


WP1000: SPS Mandatory I/F Development


Activities performed
  • Installation at ESRIN concluded - fix made to Tomcat installation and software fully tested.
  • Presentation of work to Ground Segment Coordination Body (18/19 June)


Outcomes and results

  • Software installed

Problems and concerns
  • None

Plans for next period
  • Preparation of progress report on HMA-T Wiki.