Project Manager Assessment


The status of the project is nominal.

Key Problem List

  • None

Risk Table

  • None

Deliverables List

  • Software Requirements Document has been reviewed
  • Architecture Design Document has been reviewed
  • System Test Specification Document has been reviewed

WP1000: SPS Mandatory I/F Development


Activities performed
  • Installation at ESRIN discussed via email with Paulo Sacramento and Yves Coene

Outcomes and results
  • Ongoing installation discussion

Problems and concerns
  • None

Plans for next period
  • Solve software installation issues at ESRIN.
  • Preparation of progress report on HMA-T Wiki.
  • Preparation for and attendance at GSCB Workshop (18/19 June).