HMA-T Progress DEIMOS 0902

!HMA-T Progress February 2009 DEIMOS

Project Manager Assessment


The status of the project is nominal.

Key Problem List

  • None

Risk Table

  • None

Deliverables List

  • Software Requirements Document has been reviewed
  • Architecture Design Document has been reviewed
  • System Test Specification Document has been reviewed


WP1000: SPS Mandatory I/F Development


Activities performed
  • Acceptance Review 1 attended.
  • Software Test Specification - first draft completed. RIDs received and discussed at Acceptance Review 1
  • Development of DEIMOS SPS has been completed, following the updates to use final verison of SPS library and specification
  • Software Testing has been carried out and Test Execution Records created

Outcomes and results
  • Final SRD
  • Nearly final ADD - 1 RID requiring update
  • Nearly final STS - 2 RIDs requiring updates
  • Finished and tested development


Problems and concerns

  • None

Plans for next period
  • Get software installed at ESRIN.
  • RIDs on Software Testing Plan
  • RID on ADD
  • Preparation of progress report on HMA-T Wiki