HMA-T Progress DEIMOS 0808

HMA-T Progress August 2008 DEIMOS

Project Manager Assessment


The status of the project is nominal.

Key Problem List

  • None

Risk Table

None

Deliverables List


No items have been delivered

WP1000: SPS Mandatory I/F Development


Activities performed

  • Work has continued on the System Requirement document, assuming that SPS version 0.9.5 is the baseline. SRD may change depending on the the discussions held on the technical meeting about new version of SPS
  • Work has started on the Architecture Design document, assuming that SPS version 0.9.5 is the baseline. Again, this may change depending on the the discussions held on the technical meeting about new version of SPS
  • Discussion between DEIMOS and SPOT of technical meeting about new version of SPS at Spot Image in Toulouse (September 9 2008). Having discussed with SPOT the proposed approach to asynchronous processing we have decided DEIMOS will not attend the teleconference directly.


Outcomes and results

  • On-going SRD
  • On-going ADD


Problems and concerns

  • Impact of forthcoming 07-018 EO Profile for SPS.


Plans for next period

  • Consolidating the SRD and ADD.
  • Preparation of progress report on HMA-T Wiki.
  • Establishing useful set of Radar tasking parameters to use.