HMA-T Progress DEIMOS 0807

HMA-T Progress July 2008 DEIMOS

Project Manager Assessment


The status of the project is nominal.

Key Problem List

  • None

Risk Table

None

Deliverables List


No items have been delivered

WP1000: SPS Mandatory I/F Development


Activities performed

  • Work has started on the System Requirement document, assuming that SPS version 0.9.5 is the baseline. SRD may change depending on the the discussions held on the technical meeting about new version of SPS


Outcomes and results

  • On-going SRD


Problems and concerns

  • Impact of forthcoming 07-018 EO Profile for SPS.


Plans for next period

  • Participation to technical meeting about new version of SPS at Spot Image in Toulouse (September 9 2008). Topics to be addressed: synchronous operations, use of ws-notification, impact on ordering ICD etc.
  • Consolidation of the SRD.
  • Preparation of progress report on HMA-T Wiki.