HMA-T Progress CNR-IMAA 0905

Project Manager Assessment


Key Problem List

* The following concerns must be considered, in order to schedule an effective timeline:
* Standard and requirement specifications (i.e. EO EP, HMA-T Community Profile) should be finalized as soon as possible
* A more mature version of the ERGO TEAM Engine (including documentation) should be provided as soon as possible
* Persistent server endpoints to be tested should be identified as soon as possible

Risk Table

* none

Deliverables List

The following documents have been delivered:
* Comments on EO EP Compliance Test implementation in the framework of HMA-2

WP-0 Project Management

Activities performed
* Management
* Internal monthly meeting with PIN-UoF (subcontractor of CNR-IMAA) for coordination

Outcomes and results
* Monitoring of activities

Problems and concerns
* none

Plans for next period
* Project Management

WP-1 Implementation and Test

Activities performed
* maintenance and improvement of implementation of ESA catalog specifications in GI-cat

Outcomes and results
* beta version of ESA catalogs support in GI-cat

Problems and concerns
* none

Plans for next period
* Final release of implementation of ESA catalog specifications in GI-cat

WP-2 Demonstration

Activities performed
* not yet started

Outcomes and results
* none

Problems and concerns
* none

Plans for next period
* none (WP-2 is planned to start after WP-3)

WP-3 Conformance Test

Activities performed
* implementation of ETS

Outcomes and results
* Preliminary results from service endpoints provided by the HMA-T partners

Problems and concerns
* see above

Plans for next period
* to continue implementing ETS
* to continue testing HMA-T endpoints