HMA-T Progress CNR-IMAA 0902

Project Manager Assessment


The status of the project is nominal.

Key Problem List


  • none

Risk Table

  • none

Deliverables List


The following documents have been delivered:

  • IMAA-CNR Datapack - Conformance Testing 11/02/09 containing ATS's v.1.0.1, ETS's and documentation




WP-0 Project Management


Activities performed
  • Management
  • Internal monthly meeting with PIN-UoF (subcontractor of CNR-IMAA) for coordination

Outcomes and results
  • Activities started

Problems and concerns
  • none

Plans for next period
  • Project Management

WP-1  Implementation and Test


Activities performed
  • End of the first cycle of implementation of ESA catalog specifications in GI-cat

Outcomes and results
  • alpha version of ESA catalogs support in GI-cat

Problems and concerns
  • It would be useful to have a reference dataset for testing local database access

Plans for next period
  • Start of the second cycle of implementation of ESA catalog specifications in GI-cat

WP-2  Demonstration


Activities performed
  • not yet started

Outcomes and results
  • none

Problems and concerns
  • none

Plans for next period
  • none (WP-2 is planned to start after WP-3)

WP-3  Conformance Test


Activities performed
  • update of ATS's to the latest revision of ebRIM AP

Outcomes and results
  • Abstract Test Suite-CSW.ebRIM EO v.1.0.1

* Abstract Test Suite-CSW.ebRIM CIM v.1.0.1

* IMAA-CNR Datapack - Conformance Testing 11/02/09

* documentation


Problems and concerns

  • lack of ETS for CSW and ebRIM AP

Plans for next period

  * deployment, validation and support phase


Contributors to this page: Lorenzo Bigagli .

Page last modified on Monday 27 of April 2009 16:03:28 CEST by Lorenzo Bigagli.