Project Manager Assessment


The status of the project is nominal.

Key Problem List


  • none

Risk Table

  • none

Deliverables List


The following documents have been delivered:

  • Abstract Test Suite-CSW.ebRIM EO v.0.2



WP-0 Project Management


Activities performed
  • Management
  • Internal monthly meeting with PIN-UoF (subcontractor of CNR-IMAA) for coordination

Outcomes and results
  • Activities started

Problems and concerns
  • none

Plans for next period
  • Project Management

WP-1  Implementation and Test


Activities performed
  • Start of first cycle of implementation of ESA catalog specifications in GI-cat

Outcomes and results
  • early alpha version of ESA catalogs support in GI-cat

Problems and concerns
  • It would be useful to have the mapping of the ebRIM/CIM to ISO 19139 instead of ISO 19115/19119

Plans for next period
  • End of the first cycle of implementation of ESA catalog specifications in GI-cat

WP-2  Demonstration


Activities performed
  • not yet started

Outcomes and results
  • none

Problems and concerns
  • none

Plans for next period
  • none (WP-2 is planned to start after WP-3)

WP-3  Conformance Test


Activities performed
  • Alignment to CSW-ebRIM 1.0 Extension Package for Earth Observation Products (OGC 06-131r5) v.0.2.2 and to IGN Testing Policy, rev. 0

Outcomes and results
  • Abstract Test Suite-CSW.ebRIM EO v.0.2

Problems and concerns
  • none

Plans for next period

  *Finalization of ATS's, drafting of ETS's

 

 

 