HMA-T Progress CNR-IMAA 0807

Project Manager Assessment


The status of the project is nominal.

Key Problem List

  • none

Risk Table
  • none

Deliverables List


The following documents have been delivered:

  • Description of project within HMA-T wiki

WP-0 Project Management


Activities performed

  • Familarization with tools and procedures
  • Updating of Wiki pages
  • Internal meeting with PIN-UoF (subcontractor of CNR-IMAA) to: report results of KO, preliminary definition of activities, coordination


Outcomes and results

  • Activities ready to start
  • Setup of internal working group


Problems and concerns

  • none


Plans for next period

  • Project Management

WP-1 Implementation and Test


Activities performed

  • not yet started


Outcomes and results

  • none


Problems and concerns

  • none


Plans for next period

  • Requirements analysis for Reference Implementation design

WP-2 Demonstration


Activities performed

  • not yet started


Outcomes and results

  • none


Problems and concerns

  • none


Plans for next period

  • none (WP-2 is planned to start after WP-3)

WP-3 Conformance Test


Activities performed

  • not yet started


Outcomes and results

  • none


Problems and concerns

  • none


Plans for next period

  • none (WP-3 is planned to start after WP-1)