HMA-T Contribution IGN
HMA-T Contribution IGN
The objective of IGN's involvement is to develop conformance tests for the two HMA Catalog Protocols : OGC 06-131 - EO Extension Package and OGC 07-038 - CIM Extension Package.
Our activities are organized as follows:
WP0 – Management
This work package concerns the technical management of IGN's work.
It will include the following activities:
- General management of IGN’s technical work described in this proposal.
- Inputs to the Project Management Plan to be prepared by SPACEBEL;
- Inputs to the Installation Plan concerning IGN’s deliverable items;
- Monthly progress reports to SPACEBEL, inputs to the progress meetings’ agendas and any required documentation on IGN’s work to support decisions during the progress meetings;
- Management of the collaborations between IGN and software developers of implementations of OGC 06-131 and 07-038 concerning the use of the executable test scripts. E-mail exchanges and teleconferences will be organized if necessary. IGN will also report to SPACEBEL and ESA on the issues encountered.
WP1 - Improve the test policies and procedures
This work package will consist in defining or improving ESA’s test policies and procedures based on OGC document 03-085r2 Compliance Testing Program and any ESA documentation describing the procedures for using the ESA implementation of the TEAM engine. This WP covers Objective I15.1 of HMA-T Phase 2 Statement of Work.
It will include:
- The definition of the required steps to develop and validate compliance tests for HMA specifications;
- The general rules to determine compliance to an HMA specification when applying the test scripts;
- The format of compliance results’ documentation and of compliance certificates;
- The way and necessary steps to settle disputes over the results of compliance test.
Deliverables :
~~#3300CC:2008.08.25 - HMA-T Phase 2 Testing Policy - Draft 1~~
WP 2 - Develop CITE conformance test scripts for HMA Catalog Protocol OGC 06-131
This work package aims at:
- Improving the Abstract Test Suite (ATS) of the HMA Catalog Protocol OGC 06-131;
- Developing on the basis of this ATS an Executable Test Suite (ETS) compatible with the ESA Testing Platform based on the OGC TEAM Engine;
- Deploying the executable test suite on the ESA Testing Platform and validating it against the reference implementation of HMA Catalog Protocol OGC 06-131;
- Providing a support to ESA, Spacebel and the points of contact of the candidate implementations of HMA Catalog Protocol OGC 06-131 concerning this ATS and this ETS.
WP 3 - Develop CITE conformance test scripts for HMA Catalog Protocol OGC 07-038
This work package aims at:
- Developing the Abstract Test Suite (ATS) of the HMA Catalog Protocol OGC 07-038;
- Developing on the basis of this ATS an Executable Test Suite (ETS) compatible with the ESA Testing Platform based on the OGC TEAM Engine;
- Deploying the executable test suite on the ESA Testing Platform and validating it against the reference implementation of HMA Catalog Protocol OGC 07-038;
- Providing a support to ESA, Spacebel and the points of contact of the candidate implementations of HMA Catalog Protocol OGC 07-038 concerning this ATS and this ETS.
- Template for Abstract Test Suite (ATS) documentation, Acceptance Test Plan for ATS and Executable Test Scripts (ETS) documentation
- Updated Abstract Test Suite and Executable Test Scripts for OGC 06-131
- Abstract Test Suite and Executable Test Scripts for OGC 07-038
August 08 : template for ATS documentation, Acceptance Test Plan for ATS and ETS documentation
August 08 – November 08 :
ATS and ETS for OGC 06-131
October 08 – January 09:
ATS and ETS for OGC 07-038
- OGC 06-131 - EO Extension Package
- OGC 07-038 - CIM Extension Package