HMA-FO Progress Task 4 1009
HMA-FO Progress Task 4 1009
Project Manager Assessment
· The status of the project is nominal.
Key Problem List
· None
Deliverables Table
· Ordering Services for Earth Observation Products OGC 06-141r4 V0.9.6
· OPGW SDD V1.1 25/06/2011
· OPGW SRS V1.1 25/06/2011
· OPGW SID V1.0 25/06/2011
· OPGW SVS V1.0 25/06/2011
· Ordering Services for Earth Observation Products - Executable Test Suite V1.0 draft 23/06/2010
WP-10000: Project Management
Activities performed
WP-11000: Technical coordination
Set-up SWG voting for going public; management of results; communication of results to OGC and preparation of Press release for going public.
WP-12000: Configuration Management
None
WP-13000: Quality Assurance
None
WP-14000: OGC TC Meetings Attendance
Attendance to the Toulouse TC Meeting (22/09/2010)
Preparation of SWG Presentation and discussion
Preparation of presentations for opening and closing plenary
WP-20000: Engineering
Activities performed
WP-21000: Order Server Technical Specification and Architectural Design
None.
WP-22000: HMA Ordering ICD Update
OGC 06-141r4 V0.9.6 has been delivered implementing 7 issues.
WP-23000 : Order Server Acceptance Test Plan Definition
None
WP-24000 : Test Suite Definition (ATS, ETS)
Alignement of ETS to Ordering ICD V0.9.6
WP-25000: HMA Ordering ICD contribution (con terra)
Further reviewof latest version of Ordering ICD
Attendance to TC Meeting in Toulouse
Outcome and results
None
Problems and concerns
None
Plans for next period
None
WP-30000: Implementation and Testing
Activities performed
WP-31000: Order Server Design and Development
None.
WP-32000: SSE Integration Support
None
WP-33000: Order Server Acceptance Testing
None.
WP-34000: Support to Order Server Acceptance Testing
None
Outcome and results
None
Problems and concerns
None
Plans for next period