HMA-FO Progress Task 4 1006
HMA-FO Progress Task 4 1006
Project Manager Assessment
· The status of the project is nominal.
Key Problem List
· None
Deliverables Table
· Ordering Services for Earth Observation Products OGC 06-141r2 V0.9.5 draft 3
· OPGW SDD V1.1 25/06/2011
· OPGW SRS V1.1 25/06/2011
· OPGW SID V1.0 25/06/2011
· OPGW SVS V1.0 25/06/2011
· Ordering Services for Earth Observation Products - Executable Test Suite V1.0 draft 23/06/2010
WP-10000: Project Management
Activities performed
WP-11000: Technical coordination
Finalization of documents for MTR (early July).
WP-12000: Configuration Management
None
WP-13000: Quality Assurance
Reviewing of documents to be delivered for MTR
WP-14000: OGC TC Meetings Attendance
Preparation of Technical Note analyzing the different distributed scenarios for GetQuotation operation.
WP-20000: Engineering
Activities performed
WP-21000: Order Server Technical Specification and Architectural Design
Updated SRS and SDD taking into account the changes on the Ordering specification.
WP-22000: HMA Ordering ICD Update
On-going update of Ordering ICD for fixing several issues raised on the OGC Issue Tracker.
WP-23000 : Order Server Acceptance Test Plan Definition
On-going preparation of V1.0 of OPGW Software Validation Specification re-using and updating the SVTS prepared in the HMA-E project.
WP-24000 : Test Suite Definition (ATS, ETS)
First version of ETS TN and ETS itself delivered by conterra.
Preparation of MTR
WP-25000: HMA Ordering ICD contribution (con terra)
None
Outcome and results
None
Problems and concerns
None
Plans for next period
None
WP-30000: Implementation and Testing
Activities performed
WP-31000: Order Server Design and Development
On-going preparation of first version of OPGW Software Installation Document re-using the one prepared for HMA-E project.
WP-32000: SSE Integration Support
None
WP-33000: Order Server Acceptance Testing
None.
WP-34000: Support to Order Server Acceptance Testing
None
Outcome and results
None
Problems and concerns
None