This progress report covers the activities performed in December 2009.

Project Manager Assessment

  • The status of the project is nominal.

Key Problem List

  • None

Deliverables Table

  • OSEOP Charter
  • OGC 06-141 V0.9.4 
  • OGC 06-141 V0.9.5 draft 1
  • SOFTWARE DEVELOPMENT PLAN FOR HMA FOLLOW ON TASK 4 – ORDER (SDP)
  • SOFTWARE PRODUCT ASSURANCE PLAN FOR HMA FOLLOW ON (SPAP)
  • ATS first draft

WP-10000: Project Management

Activities performed

  • WP-11000: Technical coordination
    • Preparation and attendance of progress teleconference
  • WP-12000: Configuration Management
    • None
  • WP-13000: Quality Assurance
    • None
  • WP-14000: OGC TC Meetings Attendance
    • Order SWG teleconference #2 held on 17/12/2009
      •                Clarified some points raised by EUMETSAT;
      •                Gathered further information about scene selection option;

Outcome and results

  • Progress Reports
  • Minutes of Meeting

Problems and concerns

  • None 

Plans for next period

  • To attend next progress teleconf
  • To attend next SWG teleconf

WP-20000: Engineering

Activities performed

  • WP-21000: Order Server Technical Specification and Architectural Design
    •                Going-on preparation of OPGW documentation:
      •                OPGW SRS
      •                OPGW SDD
  • WP-22000: HMA Ordering ICD Update
    •                Going on preparation of second draft of Order ICD V0.9.5:
      • Closing the scene selection options issue
      • Closing other minor issues
      • Addressing comments from RFC review
  • WP-23000 : Order Server Acceptance Test Plan Definition
    • Not Started Yet.
  • WP-24000 : Test Suite Definition (ATS, ETS)
    • First draft of ATS on Ordering prepared and internally reviewed;
    • started activities on ETS
  • WP-25000: HMA Ordering ICD contribution (con terra)
    • Further issues tracked on OGC issue tracker
    • attendance to teleconference

Outcome and results

  • First Draft of ATS delivered and internally reviewed.

Problems and concerns

  • No major problems

Plans for next period

  • Going on preparation of next draft of OGC 06-141 V0.9.5.

WP-30000: Implementation and Testing

Activities performed

  • WP-31000: Order Server Design and Development
    • Not started yet.
  • WP-32000: SSE Integration Support
    • Not started yet.
  • WP-33000: Order Server Acceptance Testing
    • Not started yet.
  • WP-34000: Support to Order Server  Acceptance Testing
    • Not started yet.

Outcome and results

  • None

Problems and concerns

  • None

Plans for next period

  • None

 

 

 