ERGO PROGRESS 0904 INTECS

ERGO Progress April 2009: Intecs

 

Project Manager Assessment

 

The HMA-T deliverables are late. The final version of the testing policy and the ETS for the CIM and EOP has not been delivered yet. Intecs needs at least two weeks to check the tests and complement them with additional tests covering the ERGO requirements. A first version of the ATP including a draft the ATS test defined by CNR in the context of the HMA-T project has been prepared. The CDR is foreseen by the 8th of May. The AR is foreseen by the 9/19 of June.

Key Problem List 

 


  • The ERGO schedule is not compliant with the new HMA-T Schedule. Thus the a planning has been agreed with ESA. The late delivery of the testing policies is becoming an issue. The consortium woud like to finalize the project by middle of June (for budget and planning reasons). A draft conformance test plan has been included in the ATP and will be delivered at the CDR.

Risk Table
ID Risk Title Severity Likelihood Risk Index Risk Domain Action and status
1 Availability of HMA-T testing guidelines 3 3 9 Schedule Monitor HMA-T progress reports
2 CIM extension package availability 3 3 9 Schedule and Cost

Monitorthe extension package status and discuss with F.H.

The late delivery of the testing policies is becoming an issue. The consortium woud like to finalize the project by middle of June (for budget and planning reasons). Thus if the conformance tests will not be delivered in time (by the 17th of April) Intecs will provide additional tests to cover the requirements and the conformance tests will be skipped or an alternative solution will be agreed with ESA (e.g. Change Request). 

Regarding the CIM extension package, a draft version of the extension package has been provided by F. Houbie. The specification i under review and will be officially released in May. The reale date is not in line with the ERGO implementation. Thus, we are planning to develope the draft specification. If something will change in the final version, the modifications will be agreed with ESA (e.g. Change Request).

Deliverables List

The following documents have been delivered:

  • ERGO-PMP-1000-INT, Project Management Plan, Issue 1, revision 3, 30/04/2009
  • ERG-ADD-3100-INT, EbRIM implementation with GeoNetwork and OMAR, Toolbox Architectural Design Document, Issue 1, revision 2, 30/04/2009 (Clean document no revisions)
  • ERGO-ebRR-ADD-4CT, ERGO ebRR Architectural design Document, issue 1, revision 0, 24/04/2009
  • ERG-SRD-2100-INT, ERGO Toolbox Software requirement Document, issue 1, revision 2, 30/04/09
  • ERG-SUM-3100-INT, ERGO Toolbox Software User Manual, issue 1, Revision 0, 30/04/09.
WP1000: Project Management


Activities performed 

  • A progress meeting has been prepared and held (16/04/09)
  • Additional tests have been done on the TEAM Engine. Some bugs have been fixed.
  • The new version of the SPMP taking into account the new planning has been preparedand delivered to ESA 30/04/09
  • The documents for the CDR have been reviewed and delivered to ESA. Some deliverables are late and will be delivered beginning of may.
  • New contacts with the OGC for the article preparation.

 

Outcomes and results

  • ERGO-PMP-1000-INT, Project Management Plan, Issue 1, revision 3, 30/04/2009
  • ERGO-ebRR-ADD-4CT, ERGO ebRR Architectural design Document, issue 1, revision 0, 24/04/2009


Problems and concerns

  • See "key problem list" and "risks" ections.


Plans for next period

  • CDR preparation and attendance
  • The TEAM Engie code will be further tested.

 

WP2100: Requirement definition


Activities performed

  • none.


Outcomes and results

  • none.


Problems and concerns

  • none.


Plans for next period

  • This WP has been completed

 

WP3100 Integration of the OMAR open source implementation in the SSE Toolbox


Activities performed

  • The Toolbox SRD has been updated in order to remove some obsolete requirements and has beendelivered to ESA.
  • The ADD has been prepared and delivered to ESA.
  • The SUM has been prepared and delivered to ESA.
  • Toolbox has been tested with SRD test cases and bugs have been fixed when found
  • Started regression tests in order to check coverage of older requirements. Fixed bugs when found


Outcomes and results

  • ERG-ADD-3100-INT, EbRIM implementation with GeoNetwork and OMAR, Toolbox Architectural Design Document, Issue 1, revision 2, 30/04/2009
  • ERG-SRD-2100-INT, ERGO Toolbox Software requirement Document, issue 1, revision 2, 30/04/09
  • ERG-SUM-3100-INT, ERGO Toolbox Software User Manual, issue 1, Revision 0, 30/04/09.

Problems and concerns

  • none.


Plans for next period

  • none

 

WP4100 Validation and Conformance testing


Activities performed

  • A first version of the ATPs for the 3 packages have been prepared. No input has been received from HMA-T yet. Thus the ATP includes the old ATS tests defined by CNR plus additional test defined by Intecs to cover the ERGO specific requirements (e.g. performances).
  • The ATP has been finalized (at TS and TC level, no procedures have been delivered yet) and delivered to ESA.

Outcomes and results

  • ERGO-EBRR-ATP-4100-INT, ebRR Acceptance Test Plan, issue 1, revision 0, 30/04/09
  • ERG-GEON-ATP-4100-INT, GeoNetwork Acceptance Test Plan, issue 1, revision 0, 30/04/09
  • ERG-ATP-4100-INT, Toolbox Acceptance Test Plan, issue 1, revision 0, 30/04/09

 

Problems and concerns

  • None


Plans for next period

  • The RIDs will be processed and the ATPs will be updated.
  • The CTL development will start and the tests will be executed.

 