ERGO Progress February 2009: Intecs

Project Manager Assessment

The HMA-T deliverables are late. According to the PMP delivered middle of February the next milestones should be: CDR - 17th of March and AR - 16th of April.
The ERGO schedule is not compliant with the new HMA-T Schedule. Thus the new planning have to be discussed with the partners and ESA.

Key Problem List 
  • The ERGO schedule is not compliant with the new HMA-T Schedule. Thus the new planning have to be discussed with the partners and ESA.
Risk Table
ID Risk Title Severity Likelihood Risk Index Risk Domain Action and status
1 Availability of HMA-T testing guidelines 3 3 9 Schedule Monitor HMA-T progress reports
2 CIM extension package availability 3 3 9 Schedule and Cost

Monitorthe extension package status and discuss with F.H.

The HMA-T deliverables are late. According to the PMP delivered middle of February the next milestones should be: CDR - 17th of March and AR - 16th of April. The ERGO schedule has to be reviewed. According to the HMA-T review results the final version of the HMA-T testing guidelines and the ETS for the CIM extension package and the EO extension profile will be available by middle April. Thus the ERGO CDR can be scheduled by the end of April.

Regarding the CIM extension package, a draft version of the extension package has been provided by F. Houbie. The specification i under review and will be officially released in May. The reale date is not in line with the ERGO implementation. Thus, we are planning to develope the draft specification. If something will change in the final version, the modifications will be agreed with ESA (e.g. Change Request)

Deliverables List

The following documents have been delivered:

  •   ERGO-SPMP-1000-INT: Ergo project Management Plan, issie 1.2, date 12/02/2009 
WP1000: Project Management


Activities performed

  • As agreed with ESA, testing activities will be based on rules defined in the HMA-T project. As output of this project a set of HMA Testing Policy will be defined. These testing policies will be the basis for the ERGO validation and conformance tests. The document describing such policies has not been released yet. Thus the ERGO testing activities cannot be finalized by the 13th of February. It has been agreed with ESA to rejoin the two development plan and have a unique CDR (17th of March) and AR (16th of April).
  • A new Project Management Plan has been prepared and delivered to ESA.
  • A progress meeting has been prepared and held (17/02/2009).
  • The work on TEAM engine has been continued.


Outcomes and results

  • ERGO-SPMP-1000-INT: Ergo project Management Plan, issie 1.2, date 12/02/2009.


Problems and concerns

  • See "key problem list" and "risks" ections..


Plans for next period

  • The PMP will be updated and delivered to ESA.

 

WP2100: Requirement definition


Activities performed

  • none.


Outcomes and results

  • none.


Problems and concerns

  • none.


Plans for next period

  • This WP has been completed

 

WP3100 Integration of the OMAR open source implementation in the SSE Toolbox


Activities performed

  • ebRR code moved from individual environment into the TOOLBOX code. API have been switched from networked version to direct access.
  • Started implementing of configuration of ebRR via the TOOLBOX Administration web pages.
  • Completing implementing the Harvesting via the TOOLBOX Administration web pages.
  • Added catalogue service configuration via Administration web pages. d


Outcomes and results

  • none.


Problems and concerns

  • none.


Plans for next period

  • none

 

WP4100 Validation and Conformance testing


Activities performed

  • Continue writing tests for the EO Application Profile (OGC 06-131r5) of csw-ebRIM. The aim of the tests is to cover the requirements that will not be covered by the conformance tests (e.g. performance).

Outcomes and results

None


Problems and concerns

None

Plans for next period

  • A first draft of the Test suite for the csw-ebRIM EO Application Profile

Contributors to this page: