ERGO PROGRESS 0901 INTECS

ERGO Progress January 2009: Intecs 

Project Manager Assessment

As agreed with ESA, testing activities will be based on rules defined in the HMA-T project. As output of this project a set of HMA Testing Policy will be defined. These testing policies will be the basis for the ERGO validation and conformance tests. The document describing such policies has not been released yet. Thus the ERGO testing activities cannot be finalized by the 13th of February. It has been agreed with ESA to rejoin the two development plan and have a unique CDR (17th of March) and AR (16th of April).  

The PMP will be updated in the next weeks and delivered to ESA

Key Problem List
  • None
Risk Table
ID Risk Title Severity Likelihood Risk Index Risk Domain Action and status
1 Availability of HMA-T testing guidelines 3 3 9 Schedule Monitor HMA-T progress reports
2 CIM extension package availability 3 3 9 Schedule and Cost

Monitorthe extension package status and discuss with F.H.

 

Deliverables List

 

The following documents have been delivered:

  • none

 

WP1000: Project Management


Activities performed

  • A progress meeting has been prepared and held (23/01/2009).
  • An additional meeting with ESA has been done to discuss the planning and define the next steps (26/01/2009). Testing activities will be based on rules defined in the HMA-T project. As output of this project a set of HMA Testing Policy will be defined. These testing policies will be the basis for the ERGO validation and conformance tests. The document describing such policies has not been released yet. Thus the ERGO testing activities cannot be finalized by the 13th of February. It has been agreed with ESA to rejoin the two development plan and have a unique CDR (17th of March) and AR (16th of April).
  • The work on TEAM engine has been restrted.


Outcomes and results

  • none.


Problems and concerns

  • none.


Plans for next period

  • The PMP will be updated and delivered to ESA.

 

WP2100: Requirement definition


Activities performed

  • none.


Outcomes and results

  • none.


Problems and concerns

  • none.


Plans for next period

  • This WP has been completed

 

WP3100 Integration of the OMAR open source implementation in the SSE Toolbox


Activities performed

  • Implemented GetRecords, GetRecordsById and Harvest operations
  • Created some use cases for testing implemented operations. Fixed found bugs in Toolbox and ebRR.
  • Refinement of operation logic for StandAlone service.
  • Started implementation of all other operations.
  • The preparation of the test documents has been continued


Outcomes and results

  • none.


Problems and concerns

  • none.


Plans for next period

  • none

 

WP4100 Validation and Conformance testing


Activities performed

Start writing tests for the EO Application Profile (OGC 06-131r5) of csw-ebRIM:

 

Selection of the collections to performs tests and analysis of the query criteria to be supported




Outcomes and results

None



Problems and concerns

None



Plans for next period

A first draft of the Test suite for the csw-ebRIM EO Application Profile

 