ERGO Progress December 2008: Intecs

Project Manager Assessment

The Project Management plan has been updated according to the new plan proposed at the PM3.
The following meeting schedule has been agreed with ESA and the partners. The exact date meeting may change to optimize travels.

  

Milestone
Name
Location
Major Deliverables
Time
M1-KO
Kick-off
ESRIN
Project Management Plan
Product Assurance Plan
1 April 2008
M2-PDR
Preliminary Design Review
Intecs
Requirement Baseline Document
23 May 2008
M3–CDR 4CT - INT
Critical Design Review (EbRR & Toolbox)
Foresee technologies
Un-validate software
13 February 2009
M4-AR 4CT – INT
Acceptance Review(EbRR & Toolbox)
Intecs
Architectural Design document
Acceptance Test Document(s)
Validated software
16 March 2009
M5–CDR GeoC
Critical Design Review (GeoNetwork)
Intecs
Un-validate software
16 March 2009
   
GeoCat B.V.
Architectural Design document
Acceptance Test Document(s)
Validated software
7 April 2009
M7–FP
Final Presentation
ESRIN
Project Executive Summary
30 April 2009
 

Key Problem List
  • None
Risk Table


ID Risk Title Severity Likelihood Risk Index Risk Domain Action and status
1 - - - - - -
2 - - - - - -


 

Deliverables List


The following documents have been delivered:

  • none
WP1000: Project Management


Activities performed

  • The PMP has been updated according to the new plan
  • A template for the ADD has been prepared and sent to the partners.
  • A first version of the EbRR ADD has been received anc checked. Some internal RIDs have been sent to 4CT


Outcomes and results
 

  • New project plan.


Problems and concerns
 

  • none.


Plans for next period
 

  • A PM will be prepared and held
  • review of the partners ADD
 
WP2100: Requirement definition


Activities performed
 

  • This WP has been completed.


Outcomes and results
 

  • none.


Problems and concerns
 

  • none.


Plans for next period
 

  • This WP has been completed
WP3100 Integration of the OMAR open source implementation in the SSE Toolbox


Activities performed

  • Finalized handling logic for catalogue services.
  • Started integrating ebRR code into Toolbox.
  • A new plugin has been created for providing catalogue interfaces.
  • A new plugin has been created for providing ebRR specific scripting tags.
  • The development of the standalone catalogue service has been started.

 
Outcomes and results
 

  • none.


Problems and concerns
 

  • none.


Plans for next period
 

  • Link to the ebRR catalogue will be finalized.
  • ebRR catalogue will be integrated into Toolbox, moving the connection between network based to Java call based.
WP4100 Validation and Conformance testing

Activities performed
 

  • The preparation of the validation test documentation has been started (for the EbRR and Toolbox)


Outcomes and results
 

  • none.


Problems and concerns
 

  • none.


Plans for next period
 

  • The work on the documentation will be continued
  • The test scripts will be prepared

 


Contributors to this page: