ERGO PROGRESS 0811 INTECS

ERGO Progress November 2008: Intecs

Project Manager Assessment

Some delay has been accumulated by the project partners. Intecs has collected detailed information about the partners schedule and has proposed a new Schedule.

Intecs propose to split the planning in two lines. Thus 2 CDRs and two ARs are foreseen.

M3 - CDR 4CT – INT. The following items will be delivered:

  • Updated SSE Toolbox Architectural Design Document
  • Updated SSE Toolbox User Manual
  • Updated SSE Toolbox software package
  • Updated Toolbox Test Plan
  • EbRR Architectural Design Document
  • EbRR Installation and User Manual
  • EbRR software package
  • EbRR Acceptance Test Plan
  • EbRR Conformance Test Plan

M4 - AR - 4CT – INT The following items will be delivered:

  • Validated EbRR software
  • EbRR Test Data package
  • EbRR Acceptance Test report
  • EbRR Conformance test report
  • Validated Toolbox Software
  • Toolbox test Data Package
  • Toolbox Acceptance Test Report

M5 - CDR – GeoC The following items will be delivered:

  • GeoNetwork Architectural Design Document
  • GeoNetwork Installation and User Manual
  • GeoNetwork software package
  • GeoNetwork Acceptance Test Plan
  • GeoNetwork Conformance Test Plan

M6 - AR – GeoC The following items will be delivered:

  • Validated GeoNetwork software
  • GeoNetwork Test Data package
  • GeoNetwork Acceptance Test report
  • GeoNetwork Conformance test report

To minimize the impact on the travel plan the following meeting schedule is proposed

  

Milestone
Name
Location
Major Deliverables
Time
M1-KO
Kick-off
ESRIN
Project Management Plan
Product Assurance Plan
1 April 2008
M2-PDR
Preliminary Design Review
Intecs
Requirement Baseline Document
23 May 2008
M3–CDR 4CT - INT
Critical Design Review (EbRR & Toolbox)
Foresee technologies
Un-validate software
13 February 2009
M4-AR 4CT – INT
Acceptance Review(EbRR & Toolbox)
Intecs
Architectural Design document
Acceptance Test Document(s)
Validated software
16 March 2009
M5–CDR GeoC
Critical Design Review (GeoNetwork)
Intecs
Un-validate software
16 March 2009
M6-AR GeoC
Acceptance Review (GeoNetwork)
GeoCat B.V.
Architectural Design document
Acceptance Test Document(s)
Validated software
7 April 2009
M7–FP
Final Presentation
ESRIN
Project Executive Summary
30 April 2009
 

Key Problem List
  • None
Risk Table


ID Risk Title Severity Likelihood Risk Index Risk Domain Action and status
1 - - - - - -
2 - - - - - -


 

Deliverables List


The following documents have been delivered:

 

  • none
WP1000: Project Management


Activities performed
 

  • Some delay has been accumulated on the projects. A PM has been prepared and held (teleconference).
  • A new project plan has been defined and agreed with ESA and the partners.
  • A draft PMP has been prepared. The final version of the plan shall be delivered beginning on December.


Outcomes and results
 

  • New project plan.


Problems and concerns
 

  • none.


Plans for next period
 

  • Update and deliver the PMP
 
WP2100: Requirement definition


Activities performed
 

  • This WP has been completed.


Outcomes and results
 

  • none.


Problems and concerns
 

  • none.


Plans for next period
 

  • This WP has been completed
WP3100 Integration of the OMAR open source implementation in the SSE Toolbox


Activities performed
 

  • Redesigned and started development of part of the service creation code in order to properly manage different service types (standard, catalogues etc..) and to manage different service modes (e.g. Catalogues StandAlone and Gateway modes).
  • Started developing new Toolbox scripting tags in order to natively communicate with the ebRR instance. Currently SOAP version of API are used. These new tags will be used in the future to create scripts for StandAlone mode (these script shall be automatically provided by TOOLBOX).
  • Performed some code clean (expecially for the jsp part) in order to improve stability and execution speed.

 
Outcomes and results
 

  • none.


Problems and concerns
 

  • none.


Plans for next period
 

  • Starting integration of EbRR code as soon it will become available. 
WP4100 Validation and Conformance testing

Activities performed
 

  • none 


Outcomes and results
 

  • none.


Problems and concerns
 

  • none.


Plans for next period
 

  • none

 