ERGO PROGRESS 0810 GEOCAT

---

WP2300

The WP has been completed.


WP3300

Activities performed:
  • Implementation of Basic Extension package
  • Start of implementation of Search Engine
  • Start of implementation of Persistence Layer

Outcomes and results:
The above implementations have been, or are being implemented

Problems and concerns:

*A delay is foreseen due to one project member (E Tajariol) leaving the project. It took more time than expected to get good people in place to replace him. They have now started their work on the project, but a delay of two months seems inevitable. This has implications on the CDR and Final delivery dates as well as on the testing process.

Plans for next period:
Implementation of the CSW ebRIM interface, continued implementation of the Search Engine and the Persistence Layer

---

WP4300

Activities performed:
  • Continued expansion of unit test suite

Outcomes and results:
The unit test suite grows with the code base under test

Problems and concerns:
None

Plans for next period:
none