HMA-T Progress Terradue 0811
HMA-T Progress November 2008 Terradue
The status of the project is nominal
- None
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
- HMAT-SRD-0002-T2, HMA-T/G-POD Gateway Requirements Document, Issue 0.2 -
Activities performed
* Progress report
Outcomes and results
- None.
Problems and concerns
- None.
Plans for next period
* Deliver new version of SPMP with the inclusion of the PDR milestone and changes for the CITE tests sub work-package
Activities performed
- Closure of version 0.2 of the System Requirements Document (SRD)
- Update of the System Requirements Document (SRD) for the RIDs of the PDR
- Technologies assessment for the implementation of the project in particular libraries for SAML
- Update of the Architecture document following the ECSS standards.
- Closure of version 0.1 of the Architecture document
Outcomes and results
Problems and concerns
- None
Plans for next period
- Conclusion of System Requirements Document (SRD) and delivery of version 1.0
- Updates to Architecture Document
- Technologies assessment for the implementation of the project with the developments of prototypes for SAML using C#