HMA-T Progress Spot Image 0809
HMA-T Progress September 2008 Spot Image
Programming
Delivery of the Release Candidate of the SPS library delayed for one week with no impact on the project.
Draft SPS specification expected for the end of September but not released yet. Editor says he is working on it.
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
1 | OGC spec SPS v1.0 delayed | high | low | 1 | requirements baseline | Participate to telecon and OGC TC to ensure the specification is on time |
Activities performed
- Participation to technical meeting about new version of SPS at Spot Image in Toulouse (September 9 2008). Conclusion: HMA-T implementation will be based on the new version of the SPS EO.
- Participation to the OGC TC tesbed in Atlanta. SweCommon has been improved (with a positive impact on the SPS specification). WS_Notification has been discussed and accepted by the Working Group.
- Working on ADD and SRD documents.
Plans for next period
- ADD and SRD documents delivery.
- Participation to OGC TC Meeting in Valencia.
- Participation to HMA WG in Valencia.
Activities performed
- SPS Library still under development
- Release candidate will be delivered to partners on October 3
Activities performed
This activity is scheduled to start 06/10/2008.
Catalogue
Project on time.
- None
- None
The following documents have been delivered:
- None
Activities performed
- Meeting with Erdas for efforts coordination and planning.
Activities performed
- Specifications analysis
Activities performed
- This activity is scheduled to start 01/11/2008.