HMA-T Progress Spacebel 0910
HMA-T Progress September-October 2009 Spacebel
The progress on the CITE test consolidation is slow and these atasks are late. As a consequence the FP is delayed.
*None
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
1 | CITE implementations late | 3 | 2 | 6 | schedule | Monitor technical progress monthly |
2 | HMA ICD change | 2 | 3 | 9 | cost | Forsee consolidation phase at end. |
The following documents have been delivered:
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 4, 19/08/09.
Activities performed
- Update of several Wiki pages to close outstanding actions.
- Update of open action list and Wiki pages.
- teleconference 10 september IGN, ESA, Intecs.
- teleconference 14 september about user management with Eumetsat,Conterra, ESA, Intecs.
- participation to HMA AWG in Darmstadt.
- teleconference 9 october IGN, CNR, Intecs, ESA.
- Normal work
Outcomes and results
- Updated action list in MS-Excel format.
Problems and concerns
- Progress on CITE test consolidation very slow. Delivery is late and FP is delayed as a consequence.
- OGC 06-131 and OGC 07-038 documents changed at very late stage affecting implementations and CITE tests.
- Acceptance of IGN, CNR-IMAA and Infoterra activities delayed. No new date scheduled.
Plans for next period
- Participation to Security:User Management meeting in Toulouse 24 November 2009 (TBC).
Activities performed
- Finalisation of SSE CIM EP catalogue client accessing ERDAS CSW CIM EP.
- Finalisation of SSE CIM EP catalogue client accessing Intecs ERGO CIM EP.
- Participation to OGC TC in Darmstadt.
Outcomes and results
- Normal work.
Problems and concerns
- None.
Plans for next period
- This work package is completed.
Plans for next period
- None.
Activities performed
- Preparation of email lists for each task
- Initialisation of Wiki structure.
- Participation to Metadata workshop in Darmstadt 29 september.
- participation to HMA-FO meeting/teleconf on-line data access (18 september)
- Preparation of technical note skeleton for recording cross-specification issues.
Outcomes and results
- Normal work.
Problems and concerns
- None.
Plans for next period
- Normal work.
- Preparation of monthly teleconferences starting 3 november.
Activities performed
- Workpackage not yet started.
Outcomes and results
- Normal work.
Problems and concerns
- None.
Plans for next period
- None.
Activities performed
- Finalisation of open-source implementation of authentication service and publication on HMA-T wiki.
- Testing of open-source implementation authentication encryption/decryption/signatures in cooperation with Intecs;
- Finalisation of SRD, ADD and ATP documents and publication on the HMA-T wiki.
- Update and delivery of OGC 07-118 and delivery of draft version 0.0.5 before the HMA AWG in Darmstadt.
- Participation to teleconferences with ESA and Eumetsat/con terra.
- Investigation of ws-trust specification for future use in OGC 07-118.
- Communication with Intecs about changes in OGC 07-118 and impact on ATS and ETS.
- Answering RIDs from con terra on OGC 07-118 v0.0.4;
- Participation to UM discussion during HMA AWG 30 september in darmstadt.
Outcomes and results
- OGC 07-118 v0.0.5 draft (delivered 28/09/2009)
- OGC 07-118 v0.0.5 (delivered 30/10/2009)
Problems and concerns
- None.
Plans for next period
- Participation to security/user management workshop in Toulouse 24/11/09 (TBC).