HMA-T Progress Spacebel 0812
!HMA-T Progress December 2008 Spacebel
The status of the project is nominal, with the exception of the CITE tasks from IGN which have incurred a delay of about two months. IGN will propose an updated planning to limit the delay and the impact on the other partners.
*None
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
1 | CITE implementations late | 3 | 2 | 6 | schedule | Monitor technical progress monthly |
2 | HMA ICD change | 2 | 3 | 9 | cost | Forsee consolidation phase at end. |
4 | Unstable TEAM engine | 3 | 2 | 6 | quality | Early tests in ERGO |
The following documents have been delivered:
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.
Activities performed
- Update of several Wiki pages to close outstanding actions.
- Participation to OGC TC in Valencia from 1 to 4 december.
- Synchronisation with FEDEO Support activities which have been started.
- Tracking of agreed actions.
Outcomes and results
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.
Problems and concerns
- Update of OGC 07-118 (User Management) document by EO-DAIL project has been delayed.
- Updated 06-131 Version 0.2.2 not yet supported by HMA Skeleton 2.0. Framecontract to update the simulation files accordingly;
- Missing planning from IGN addressing current delays.
Plans for next period
- Organisation and preparation of AR-1 meeting, currently planned for February 18-19 2009. Dates are to be confirmed.
Activities performed
- Participation to OGC TC Meeting in Valencia (Security, Architecture, EO/CIM ext. SWG, Europe Forum).
- HMA-T presentation with support from subcontractors at Europe Forum.
- Investigation of ISO19139 issues with schemas and approach for metadata definition, also in relation with the INSPIRE MD Guidance document.
- Preparing inputs for ESA User Management presentation to HMA Architecture Board in Valencia.
Outcomes and results
- None
Problems and concerns
- None
Plans for next period
- Preparation of OGC 06-131 version 0.2.2 client to be connected to Spot Image Dali catalogue.