HMA-T Progress Spacebel 0811
!HMA-T Progress November 2008 Spacebel
The status of the project is nominal, with the exception of the CITE tasks from IGN which have incurred a delay of about two months. IGN will propose an updated planning to limit the delay and the impact on the other partners.
*None
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
1 | CITE implementations late | 3 | 2 | 6 | schedule | Monitor technical progress monthly |
2 | HMA ICD change | 2 | 3 | 9 | cost | Forsee consolidation phase at end. |
3 | Unstable TEAM engine | 3 | 2 | 6 | quality | Early tests in ERGO |
The following documents have been delivered:
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.
Activities performed
- A CCN was signed with ESRIN to accommodate contractual changes required by Spotimage.
- Tracking of actions and update of on-line actions database.
- Update of several Wiki pages to close outstanding actions.
- This month the remaining subcontract with Spot image has been signed.
- Review of draft deliverables from partners
- Providing comments on draft deliverables
- Organising PDR/Progress meeting in Hoeilaart 26 november 2008
- Preparation of HMA-T presentation at OGC Europe Forum.
Outcomes and results
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.
Problems and concerns
- Update of OGC 07-118 (User Management) document by EO-DAIL project has been delayed.
- Updated 06-131 Version 0.2.0 not yet supported by HMA Skeleton 2.0. Framecontract to update the simulation files accordingly.
Plans for next period
- Participation to OGC TC in Valencia.
- Presentation of HMA-T in OGC TC Europe Forum.
Activities performed
- None
Outcomes and results
- None
Problems and concerns
- None
Plans for next period
- Preparation of presentations at OGC TC.
- Participation to OGC TC Meeting in Valencia (Security, Architecture, EO/CIM ext. SWG, Europe Forum).