HMA-T Progress Spacebel 0809
HMA-T Progress September 2008 Spacebel
The status of the project is nominal.
- None
ID | Risk Title | Severity | Likelihood | Risk Index | Risk Domain | Action and status |
1 | CITE implementations late | 3 | 2 | 6 | schedule | Monitor technical progress monthly |
2 | HMA ICD change | 2 | 3 | 9 | cost | Forsee consolidation phase at end. |
3 | Unstable TEAM engine | 3 | 2 | 6 | quality | Early tests in ERGO |
The following documents have been delivered:
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.
Activities performed
- Update of project management plan.
- Setup of on-line action tracking system
- Participation to technical meeting related to SPS at Spotimage (9 september).
- subcontracts with IGN-F, Infoterra-UK, GIM, Con terra, Intecs, Deimos and Terradue have been signed.
- CCN for Phase 2 with ESA has been signed by ESA and Spacebel.
Outcomes and results
- HMAT-SPMP-0002-SPB, Software Project management Plan, Issue 1, revision 3, 25/08/08.
Problems and concerns
- Update of OGC 07-118 (User Management) document by EO-DAIL project has been delayed.
- Updated 06-131 Version 0.2.0 not yet supported by HMA Skeleton 2.0. Framecontract to update the simulation files accordingly.
- Spot Image requests changes to their subcontract which are not inline with the ESA draft contract. ESA has been informally requested to allow for a Waiver.
- No signed subcontract from CNR-IMAA has been received.
- CNR-IMAA email addresses are unreliable and emails bounce back in a random fashion. Alternative email addresses have been provided by CNR-IMAA for use in the email alias.
Plans for next period
- Preparation of HMA-T technical meeting 22 october in Spacebel (Hoeilaart).
- Resolution of contractual issue with Spot Image.
- Signing remaining subcontracts with ERDAS, CNR-IMAA, Spot Image.
Activities performed
- Spacebel has registered the HMA skeleton catalogue (opt/sar/eop) on the SSE Test Portal. A link to this demo will be added on the HMA Skeleton Wiki Page.
Outcomes and results
- None
Problems and concerns
- None
Plans for next period
- Preparation of presentations at OGC TC catalogue working group related to catalogue and CITE.
- Participation to OGC TC Meeting in Valencia.
- Participation to HMA WG in Valencia.