HMA-T Progress IGN 0808
HMA-T Progress July 2008 IGN
Activities performed
None.
Plans for next period
- Attend 05/09/08 teleconference
Activities performed
- Delivery of HMA-T Phase Testing Policy Technical Note. See : ~~#3300CC:2008.08.25 - HMA-T Phase 2 Testing Policy - Draft 1~~
Plans for next period
- Finalize the template for ATS and ETS documentation
Activities performed
This activity is scheduled to start at the end of August 2008.
Outcomes and results
- None
Problems and concerns
- None
Plans for next period
- Access and review the existing ATS and ETS developed by Galdos in Phase 1
- Prepare draft ATS for EO EP
- Preliminary draft of EO EP ETS
Activities performed
This activity is scheduled to start in October 2008.
Outcomes and results
- None
Problems and concerns
- None
Plans for next period
- First ideas on how to build modular CIM conformance classes