HMA-FO Progress Task 4 1008
HMA-FO Progress Task 4 1008
Project Manager Assessment
· The status of the project is nominal.
Key Problem List
· None
Deliverables Table
· Ordering Services for Earth Observation Products OGC 06-141r3 V0.9.5
· OPGW SDD V1.1 25/06/2011
· OPGW SRS V1.1 25/06/2011
· OPGW SID V1.0 25/06/2011
· OPGW SVS V1.0 25/06/2011
· Ordering Services for Earth Observation Products - Executable Test Suite V1.0 draft 23/06/2010
WP-10000: Project Management
Activities performed
WP-11000: Technical coordination
Review of MTR Minutes.
WP-12000: Configuration Management
None
WP-13000: Quality Assurance
None
WP-14000: OGC TC Meetings Attendance
None
WP-20000: Engineering
Activities performed
WP-21000: Order Server Technical Specification and Architectural Design
None.
WP-22000: HMA Ordering ICD Update
None
WP-23000 : Order Server Acceptance Test Plan Definition
None
WP-24000 : Test Suite Definition (ATS, ETS)
None
WP-25000: HMA Ordering ICD contribution (con terra)
None
Outcome and results
None
Problems and concerns
None
Plans for next period
None
WP-30000: Implementation and Testing
Activities performed
WP-31000: Order Server Design and Development
None.
WP-32000: SSE Integration Support
None
WP-33000: Order Server Acceptance Testing
None.
WP-34000: Support to Order Server Acceptance Testing
None
Outcome and results
None
Problems and concerns
None